STAY UP TO DATE
Check this page for information about the progress of the redevelopment and construction updates.


Construction Update: october 2026
- Continued construction noise expected with bulk soil deliveries.
- Increased construction traffic with concrete slab placements and wall panel deliveries.
- Start of window installation at Building 1.
- Continued site electrical work.
- Preparation for asphalt binder.
Construction Update: september 2026
- Increased construction traffic with wall panel and lumber deliveries.
- Increased noise with the start of rough framing.
- Beginning of first floor wall framing and exterior sheathing installation at Buildings 1 and 3.
- Installation of underground utilities at Buildings 5 and 6.
Construction Update: august 2026
- Increased construction traffic with wall panel and lumber deliveries
- Rough framing will begin in September (with first floor wall framing and exterior sheathing)
- Underground mechanical and plumbing systems at the buildings closest to Millstone Road
- Infill and compaction at three buildings
- Continued installation of stormwater retention chambers
- Form and placement of foundation walls and slab on grade across the site
Construction Update: july 2026
- Continued construction traffic with heavy equipment and concrete trucks
- Improvements to site entrance
- Major deliveries of site reinforcing materials (rebar and mesh)
- Beginning of excavation at three more buildings, along with damproofing and insulation
Construction Update: june 2026
- Increased construction traffic with heavy equipment and concrete trucks
- Beginning of concrete foundation work, along with damproofing and insulation
Construction Update: may 2026
- Foundation work is beginning for all buildings
- Excavators moving in and out of areas of work
- Construction site is currently using grid power, and the generator is no longer necessary
- Framing will start in July
Construction Update: april 2026
- Temporary construction fence has been installed around the perimeter of the construction area
- Rough grading is ongoing throughout the job site
- Site utility structures are being installed
- Excavation and inspections for building foundations have begun
- Foundation work will continue into May and June
Construction Update: March 2026
- Week of March 2-6
- Initial mobilization
- Site surveyors marking limits of work
- Installation of erosion controls and temporary construction fence to prepare for tree clearing
- Week of March 9-13
- Excavation company to begin land clearing
. . .
related articles
The Cape Cod Chronicle: It’s Official: Spring Rock Village Is Underway In Brewster

PRESS RELEASE: Congressman Keating joins POAH, Housing Assistance and community to celebrate Cape Cod groundbreaking
The Cape Cod Chronicle: POAH Closes On Financing For Spring Rock Village