STAY UP TO DATE
Check this page for information about the progress of the redevelopment and construction updates.

Construction Update: april 2026
- Temporary construction fence has been installed around the perimeter of the construction area
- Rough grading is ongoing throughout the job site
- Site utility structures are being installed
- Excavation and inspections for building foundations have begun
- Foundation work will continue into May and June
Construction Update: March 2026
- Week of March 2-6
- Initial mobilization
- Site surveyors marking limits of work
- Installation of erosion controls and temporary construction fence to prepare for tree clearing
- Week of March 9-13
- Excavation company to begin land clearing
. . .
related articles
The Cape Cod Chronicle: POAH Closes On Financing For Spring Rock Village

