Project Updates

STAY UP TO DATE

Check this page for information about the progress of the redevelopment and construction updates.

Construction Update: october 2026

  • Continued construction noise expected with bulk soil deliveries.
  • Increased construction traffic with concrete slab placements and wall panel deliveries.
  • Start of window installation at Building 1.
  • Continued site electrical work.
  • Preparation for asphalt binder.

Construction Update: september 2026

  • Increased construction traffic with wall panel and lumber deliveries.
  • Increased noise with the start of rough framing.
  • Beginning of first floor wall framing and exterior sheathing installation at Buildings 1 and 3.
  • Installation of underground utilities at Buildings 5 and 6.

Construction Update: august 2026

  • Increased construction traffic with wall panel and lumber deliveries
  • Rough framing will begin in September (with first floor wall framing and exterior sheathing)
  • Underground mechanical and plumbing systems at the buildings closest to Millstone Road
  • Infill and compaction at three buildings
  • Continued installation of stormwater retention chambers
  • Form and placement of foundation walls and slab on grade across the site

Construction Update: july 2026

  • Continued construction traffic with heavy equipment and concrete trucks
  • Improvements to site entrance
  • Major deliveries of site reinforcing materials (rebar and mesh)
  • Beginning of excavation at three more buildings, along with damproofing and insulation

Construction Update: june 2026

  • Increased construction traffic with heavy equipment and concrete trucks
  • Beginning of concrete foundation work, along with damproofing and insulation

Construction Update: may 2026

  • Foundation work is beginning for all buildings
  • Excavators moving in and out of areas of work
  • Construction site is currently using grid power, and the generator is no longer necessary
  • Framing will start in July

Construction Update: april 2026

  • Temporary construction fence has been installed around the perimeter of the construction area
  • Rough grading is ongoing throughout the job site
  • Site utility structures are being installed
  • Excavation and inspections for building foundations have begun
  • Foundation work will continue into May and June

Construction Update: March 2026

  • Week of March 2-6
    • Initial mobilization
    • Site surveyors marking limits of work
    • Installation of erosion controls and temporary construction fence to prepare for tree clearing
  • Week of March 9-13
    • Excavation company to begin land clearing

. . .